- Verify the ground can support the UBIU weight and outrigger pad loads before setup
- Deploy all outriggers fully and check pad contact before extending the platform arm
- Wear a harness clipped to the platform anchor points at all times in the basket
- Install traffic management on the bridge deck and beneath before deploying the unit
- Check wind speed before and during operation — cease work if limits are exceeded
- Maintain continuous communication between the platform occupants and the arm operator
- Complete the pre-use inspection of hydraulics, interlocks, and basket condition
- Ensure only trained and authorised operators control the UBIU arm and platform
- Brief the inspection or work team on the platform capacity and emergency procedures
- Keep tools and equipment secured within the platform basket to prevent drops below
|
- DON'T extend the platform arm until all outriggers are fully deployed and stable
- DON'T exceed the maximum number of persons or weight capacity of the platform basket
- DON'T operate in wind speeds above the manufacturer's stated maximum for the unit
- DON'T stand on the platform without a harness clipped to the designated anchor points
- DON'T deploy the UBIU without traffic management on and beneath the bridge
- DON'T position outrigger pads on soft ground, manhole covers, or hollow structures
- DON'T allow untrained personnel to operate the UBIU arm or position the vehicle
- DON'T lean over the platform basket edge or climb outside the basket at any time
- DON'T leave tools or equipment unsecured on the platform where they could fall below
- DON'T continue working if the hydraulic system shows warning lights or unusual behaviour