Formwork Erection and Striking

Toolbox Talk Record

Ref: TBT-CON-004  |  Issue: 1  |  Date: March 2026
PresenterProject
LocationDate

What?

Why?

Blowout riskInadequate formwork bracing or tie spacing fails under the pressure of wet concrete, causing a sudden, violent blowout.
Premature strikingRemoving formwork before concrete is strong enough causes structural collapse — only cube test results confirm readiness.
Correct sequenceStriking out of order concentrates loads on remaining supports, exceeding their capacity and causing progressive failure.
Do Don't
  • Erect formwork exactly as shown on the approved design drawings and specification.
  • Obtain a permit to load before placing any concrete into the formwork system.
  • Check formwork tie spacing and bracing are correct before the pour begins.
  • Apply release agent to formwork faces before fixing reinforcement inside.
  • Monitor formwork during the pour for signs of movement, leakage, or deflection.
  • Wait for cube test results before requesting authorisation to begin striking.
  • Follow the designed striking sequence — do not remove formwork in random order.
  • Use mechanical lifting for heavy formwork panels during erection and striking.
  • Inspect all formwork panels for damage and warping before reuse.
  • Brief the team on the formwork system, pour sequence, and striking schedule.
  • DON'T alter the formwork design on site without engineer approval.
  • DON'T pour concrete without a valid permit to load from the TW coordinator.
  • DON'T accept inadequate tie spacing or bracing — check before the pour starts.
  • DON'T omit release agent — formwork without it damages the concrete on striking.
  • DON'T ignore leaking, bulging, or deflecting formwork during a pour — stop and investigate.
  • DON'T strike formwork until cube tests confirm the concrete strength is adequate.
  • DON'T remove formwork panels out of the approved striking sequence.
  • DON'T manually lift heavy formwork components when mechanical aids are available.
  • DON'T reuse formwork that is damaged, warped, or no longer fit for purpose.
  • DON'T skip the formwork briefing — the team must understand the system and schedule.

See also: Formwork and Falsework | Concrete Pour Safety