Temporary Works for Crane Bases

Toolbox Talk Record

Ref: TBT-TWK-013  |  Issue: 1  |  Date: March 2026
PresenterProject
LocationDate

What?

Why?

Crane collapseInadequate crane base design causes ground bearing failure, outrigger punch-through, and catastrophic crane collapse.
Load transferOutrigger loads are enormous — the base must spread these loads to prevent local ground failure.
Legal requirementBS 5975 and LOLER 1998 require crane bases to be designed, checked, and managed as temporary works.
Do Don't
  • Commission a ground investigation to determine bearing capacity at the crane location
  • Design the crane base through the temporary works procedure with TWC approval
  • Verify the base construction matches the approved design before the crane arrives
  • Check for buried services, drains, and voids beneath the proposed crane base area
  • Monitor settlement of the crane base during operations, especially on first use
  • Ensure outrigger pads are positioned centrally on the designed bearing area
  • Maintain the crane base surface in good condition throughout the duration of use
  • Brief the crane operator on the base design capacity and any load restrictions
  • Record all inspections and monitoring data in the temporary works register
  • Plan and manage removal of the crane base as a temporary works activity
  • DON'T position a crane on unassessed or undesigned ground bearing surfaces
  • DON'T exceed the design load capacity of the crane base at any outrigger position
  • DON'T set up cranes over buried services or drainage without engineer assessment
  • DON'T skip the TWC approval process for crane base temporary works
  • DON'T use timber mats that are damaged, split, or undersized for the applied loads
  • DON'T ignore signs of settlement, cracking, or displacement in the crane base
  • DON'T allow water to pond on or undermine the crane base — maintain drainage
  • DON'T assume one base design suits all crane setups — each configuration needs review
  • DON'T allow other plant to track across the crane base and damage the surface
  • DON'T remove the crane base without a planned method statement and TWC involvement

See also: Temporary Works Awareness | Lifting Operations Awareness (LOLER)