CDM/General/TBT-CDM-004
Principal Contractor Duties
CDM & Legal Framework › General › Principal Contractor Duties
Principal Contractor Duties
Toolbox Talk Record
Ref: TBT-CDM-004 | Issue: 1 | Date: March 2026
| Presenter | Project | ||
| Location | Date |
What?
- The principal contractor is the organisation appointed under CDM 2015 to manage health and safety during the construction phase.
- A principal contractor must be appointed on every project where more than one contractor will work at any time.
- The principal contractor must plan, manage, monitor, and coordinate the construction phase to ensure safety for all workers.
- They must prepare the construction phase plan before the construction phase begins, setting out all management arrangements.
- The principal contractor must ensure every worker receives a site-specific induction before starting work on the project.
- Coordination of multiple contractors is a core duty — preventing dangerous interactions between overlapping work activities.
- The principal contractor must consult and engage with workers on health and safety matters that affect their work.
- They must ensure welfare facilities meet the standards set out in CDM 2015 Schedule 2 throughout the project.
- The principal contractor must monitor contractor and subcontractor compliance with site rules and safety procedures.
- Site rules, including access control, PPE requirements, and reporting procedures, must be established and enforced.
Why?
| Legal accountability | The principal contractor holds primary legal responsibility for construction phase safety — failing in this duty leads to criminal prosecution. |
| Coordination | Managing multiple contractors working simultaneously is the principal contractor's core challenge — poor coordination causes fatal interface incidents. |
| Worker protection | Every worker on site is the principal contractor's responsibility — from induction through to welfare, supervision, and emergency arrangements. |
| Do | Don't |
|
See also: CDM 2015 Awareness | Construction Phase Plan Awareness |